Free course · Foundation · 6 lessons · about 90 minutes
Project finance for EPC contractors and government tenders
A practical, self-paced course for finance and accounts teams at Indian contractors in civil, sports infrastructure, installation and similar work, bidding for government and private projects. You will follow a project from bid to defect liability, prepare tender financials, manage bank guarantees, turn running bills into cash, account for revenue over time and run the controls that keep a project from eating the company’s working capital.
What you will be able to do
- Map each stage of a project’s life to its finance tasks and cash flows
- Prepare the financial documents that prove eligibility in a tender
- Plan, price and track bank guarantees against your bank limits
- Convert a running account bill into an expected cash receipt after all deductions
- Recognise contract revenue over time and provide for an expected loss
- Control variations, claims, liquidated damages and project closure through a monthly MIS
Lesson 1: The project lifecycle through a finance lens
A contract is won by the bid team and built by engineers, but it is the finance team that funds the gap between spending and getting paid. Knowing where that gap opens and closes is the starting point for everything else.
Seven stages, seven sets of finance tasks
| Stage | What happens | What finance does | Cash direction |
|---|---|---|---|
| Bid | Tender studied, cost estimated, bid submitted | Eligibility documents, bid security, cost and margin review | Out (tender fee, bid security) |
| Award | Letter of acceptance or work order issued; agreement signed | Performance guarantee, contract register, project cost code | Out (guarantee margin and commission) |
| Mobilisation | Site set up, labour and plant moved, first materials bought | Mobilisation advance claim (if the contract allows), advance guarantee, insurance | Heavy out; advance may come in |
| Execution | Work done and measured | Cost tracking, vendor and subcontractor payments, budget versus actual | Out every month |
| Billing | Running account bills raised and certified | Bill preparation support, deductions check, receivable follow-up | In, after a delay |
| Completion and closure | Completion certificate, final bill, handover | Final bill, claims, reconciliation with the client’s ledger | In (final bill), often slow |
| Defect liability period | Contractor fixes defects for an agreed period | Track retention and guarantees, provide for rectification cost | In (retention release) at the end |
The cash curve
On almost every contract, cash goes out long before it comes in. Plot cumulative receipts minus cumulative payments month by month and you get a curve that dips deep in the early months and only climbs back above zero late in the project, sometimes not until retention is released after the defect liability period. The depth of that dip is the working capital the project needs. The length of time it stays below zero is how long your money is locked up.
Three things deepen the dip: slow certification of bills, deductions such as retention and advance recovery, and costs incurred ahead of billable milestones. Three things soften it: a mobilisation advance, back-to-back credit terms with suppliers and subcontractors, and quick, clean bills that are certified the first time.
One project, one cost centre
Give every contract its own project code from the day of award. Every purchase order, labour sheet, plant hire bill, guarantee charge and site expense should carry that code. Without it you cannot tell which project is profitable, you cannot calculate percentage of completion (lesson 5), and you cannot answer the first question a lender or auditor will ask.
Who finance works with
- Tender or bid team: eligibility, pricing assumptions, cash flow forecast for the bid.
- Project manager and site engineer: measurements, progress, cost to complete.
- Purchase and stores: material cost, site stock, subcontractor bills.
- Bankers: guarantees, working capital limits, margin money.
- The client’s engineer and accounts office: bill certification and payment.
Lesson check
Four questions. Get 3 right to complete the lesson. Your progress is saved in this browser.
Lesson 2: Tenders and bids: eligibility and the finance file
A strong technical bid can be rejected because a turnover certificate is in the wrong format or a solvency certificate is out of date. Finance owns these documents, and owning them well wins work.
Where tenders are published
Government buyers publish most tenders on electronic procurement portals: the Central Public Procurement Portal for many central bodies, state e-procurement portals for state departments, and the Government e-Marketplace (GeM), which began with goods and services and now carries some works and installation categories. Bidders register, hold a valid digital signature certificate and upload documents as scanned or signed files. Private clients and PSUs may use their own portals or paper tenders. Treat each portal’s registration and digital signature as a renewable asset with an expiry date in your compliance calendar.
The usual financial eligibility tests
| Test | What it usually means | Document finance provides |
|---|---|---|
| Average annual turnover | Average of the last few audited years must reach a set amount or percentage of the estimated cost | Audited financial statements and a CA certificate of turnover |
| Net worth | Positive, or above a minimum, at the latest balance sheet date | CA certificate of net worth with its computation |
| Similar work experience | Completed works of a stated type and value within a recent period | Completion certificates from clients, work orders, final bill values |
| Solvency | A bank’s opinion that the bidder is good for a stated amount | Solvency certificate from your banker, in the tender’s format |
| Bid capacity (some tenders) | A formula combining past turnover, existing commitments and contract period | Statement of works in hand with balance values |
The thresholds, the number of years averaged and the definition of “similar work” are set by each tender document. read the eligibility clause of each tender; there is no single national rule.
Worked example: does the turnover qualify?
A tender for a sports complex has an estimated cost of ₹20 crore. Assume it requires average annual turnover over the last three audited years of at least 30% of the estimated cost, which is ₹6 crore. Fieldline Infra Pvt Ltd has turnover of ₹5.20 crore, ₹6.80 crore and ₹7.40 crore. Total = ₹19.40 crore. Average = ₹19.40 crore ÷ 3 = ₹6.47 crore (rounded). Fieldline qualifies, but only just. If the first year had been ₹4.00 crore, the average would be ₹18.20 crore ÷ 3 = ₹6.07 crore: still in, with almost no headroom. Check which three years the tender means before you calculate.
The finance tender file
- Audited statements for at least the last five years, signed, with the audit report, in one PDF per year.
- CA certificates for turnover and net worth, with UDIN, on letterhead, worded the way the tender asks.
- Solvency certificate requested early; banks take time, and many tenders want one issued recently.
- Registration documents: PAN, GST registration, incorporation or partnership papers, MSME registration if any.
- Completion certificates indexed by client, value and completion date.
Bid security
Most tenders ask for bid security (earnest money deposit, or EMD) to stop bidders withdrawing after the deadline or refusing an award. It may be paid online, given as a bank guarantee, or, in some government tenders, replaced by a signed bid security declaration. Registered micro and small enterprises are often exempt for eligible tenders. The amount, the accepted forms and any exemption are set by the tender and the procurement rules that apply to that buyer. check the tender’s EMD clause and the current procurement rules for the buyer; exemptions and declarations vary. Track every EMD paid until it is refunded; unsuccessful bidders’ deposits are often forgotten.
Lesson check
Four questions. Get 3 right to complete the lesson. Your progress is saved in this browser.
Lesson 3: Bank guarantees in contracting
A contractor’s capacity to take on work is often limited less by engineers than by bank guarantee limits. Each guarantee uses limit, locks up margin money and costs commission, so finance has to plan them like cash.
The four guarantees you will meet
| Guarantee | When it is given | What it protects the client against | When it should come back |
|---|---|---|---|
| Bid guarantee | With the bid, in place of cash EMD | Withdrawal or refusal to sign | On award to someone else, or replaced by a performance guarantee |
| Performance guarantee | Soon after award | Failure to perform the contract | After completion and usually the defect liability period |
| Advance payment guarantee | Before a mobilisation or material advance is released | Advance not recovered | As the advance is recovered; the guarantee can often be reduced in steps |
| Retention money guarantee | To release retention held from bills | Defects during the liability period | At the end of the defect liability period |
The amount, format, validity and claim period of each guarantee are fixed by the contract. Government clients usually insist on their own format; any deviation can mean rejection. the percentage for performance security and the accepted forms are set by the tender and the buyer’s procurement rules.
How the bank sees it
A guarantee is a non-fund-based facility: no money leaves the bank unless the client invokes it. The bank sanctions a guarantee limit, takes a cash margin (often held as a fixed deposit) for part of each guarantee, may take other security, and charges commission, usually as a percentage per year or part of a year. If a guarantee is invoked, the bank pays the client and debits your account; it becomes a fund-based exposure overnight.
Worked example: the cost of one contract’s guarantees
Northpitch Projects wins a ₹40 crore contract. Assume the contract needs a performance guarantee of 5% and a mobilisation advance of 10% backed by an advance payment guarantee of the same value. Assume the bank takes 15% margin and charges commission of 1.2% a year (illustrative figures; your sanction letter decides).
| Item | Working | Amount |
|---|---|---|
| Performance guarantee | 5% × ₹40 crore | ₹2,00,00,000 |
| Advance payment guarantee | 10% × ₹40 crore | ₹4,00,00,000 |
| Guarantee limit used | ₹2 crore + ₹4 crore | ₹6,00,00,000 |
| Margin money locked | 15% × ₹6 crore | ₹90,00,000 |
| Commission for the first year | 1.2% × ₹6 crore | ₹7,20,000 |
The ₹90 lakh of margin is cash the project cannot use, and the ₹7.2 lakh of commission is a project cost that belongs in the bid estimate. If Northpitch’s total guarantee limit is ₹15 crore and ₹8 crore is already used, this one contract leaves only ₹1 crore of headroom for the next bid’s guarantees.
Run a guarantee register
- One line per guarantee: number, bank, beneficiary, project, type, amount, issue date, expiry date, claim period end, margin held, commission paid.
- Expiry alerts at 60 and 30 days. Clients often ask for extension when a project runs late; an unextended guarantee may be invoked instead.
- Reduction and return: as advances are recovered or work is completed, ask the client in writing to reduce or return the guarantee, then get the original back and give it to the bank to release the limit and the margin.
- Invocation risk: flag any project in dispute or behind schedule. An invocation should never be the first time the board hears of a problem.
Many banks and clients now use electronic bank guarantees, which reduce fraud and courier delays, but the register is still yours to maintain. check whether the client accepts electronic guarantees and the claim period your bank allows after expiry.
Lesson check
Four questions. Get 3 right to complete the lesson. Your progress is saved in this browser.
Lesson 4: Running bills, deductions and cash
The invoice value of a running bill and the cash that reaches your bank are very different numbers. Finance has to know the gap in advance, because that gap is working capital.
From measurement to money
On item-rate and most government works, the contractor is paid through running account (RA) bills: interim bills for work done to date. The client’s engineer records quantities in a measurement book, or its electronic equivalent; the quantities are priced at the contract rates; the cumulative value less the previous bills gives this bill’s value. Lump-sum and EPC contracts often bill on milestones instead. Either way, the bill is only as good as its supporting measurements. Finance should insist that the site keeps its own copy of every measurement and checks it against the certified bill.
The usual deductions
- Retention money: a percentage held back from each bill as security for performance and defects, released at completion or after the defect liability period, sometimes against a guarantee.
- Mobilisation advance recovery: the advance is recovered from bills, usually as a percentage of each bill, starting and finishing at points the contract sets. Some contracts charge interest on the advance.
- Material or secured advance recovery, where the client paid against materials brought to site.
- Tax deductions: income-tax TDS on payments to contractors and, for government and certain notified clients, TDS under GST.
- Other recoveries: materials issued by the client, water and power, penalties, and liquidated damages.
Price variation
Many longer contracts include a price variation clause: a formula that adjusts the bill for movements in published indices for materials, labour and fuel between the base date and the period of work. Finance should calculate the adjustment itself, using the indices and weights in the contract, rather than waiting for the client. Unclaimed price variation is simply lost margin.
GST and TDS on works contracts: the principles
Under GST, a works contract (construction, fabrication, installation and similar work on immovable property) is treated as a supply of services. The rate depends on the nature of the work and the client, and some government works have had special rates. Input tax credit rules for works contracts are restrictive for the client but generally allow the contractor credit on inputs used to supply works contracts. Government departments and some other notified bodies deduct TDS under GST above a contract value threshold, which the contractor claims through its electronic cash ledger. confirm the current GST rate for your type of work and client, and the GST TDS rate and threshold. Separately, income-tax TDS applies to contract payments under the Income-tax Act, 2025. confirm the current section, rate and threshold for TDS on contractor payments. Use the TDS calculator for the income-tax side.
Worked example: one RA bill
Courtline Builders raises an RA bill for work worth ₹1,00,00,000 on a state government project. Assume GST at 18%, retention at 5% of work value, mobilisation advance recovery at 10% of work value, income-tax TDS at 2% and GST TDS at 2%, both on the work value excluding GST. These rates are for illustration only.
| Line | Working | Amount |
|---|---|---|
| Work value | ₹1,00,00,000 | |
| Add GST | 18% × ₹1,00,00,000 | ₹18,00,000 |
| Bill value | ₹1,18,00,000 | |
| Less retention | 5% × ₹1,00,00,000 | ₹5,00,000 |
| Less mobilisation advance recovery | 10% × ₹1,00,00,000 | ₹10,00,000 |
| Less income-tax TDS | 2% × ₹1,00,00,000 | ₹2,00,000 |
| Less GST TDS | 2% × ₹1,00,00,000 | ₹2,00,000 |
| Net cash received | ₹1,18,00,000 − ₹19,00,000 | ₹99,00,000 |
Courtline still owes the full ₹18,00,000 of GST on the bill (less its eligible input credit), but receives ₹99 lakh, not ₹1.18 crore. The ₹2 lakh GST TDS and ₹2 lakh income-tax TDS come back only as credits; the ₹5 lakh retention comes back years later. If the client also takes 60 days to pay, the bill is funded by Courtline for two months.
Lesson check
Four questions. Get 3 right to complete the lesson. Your progress is saved in this browser.
Lesson 5: Project accounting: revenue over time and expected losses
Contract revenue in the profit and loss account is rarely the same as the amount billed. Finance has to measure progress, keep the cost-to-complete estimate honest and recognise losses as soon as they are foreseen.
Why revenue is recognised over time
When a contractor builds on the client’s land, the client controls the asset as it is built. Under Ind AS 115, revenue from such a contract is usually recognised over time, in line with progress, rather than at completion. Companies that follow the older Indian accounting standards apply AS 7, Construction Contracts, which reaches a similar answer through the percentage of completion method. Here we apply the principle to a typical works contract.
Measuring progress with the input method
Most contractors use a cost-to-cost input method: progress = costs incurred to date ÷ total estimated contract costs. Two cautions. First, only costs that reflect work actually performed count; materials delivered to site but not yet used, and costs of wasted work or rework, should normally be excluded from the progress calculation. Second, the denominator is an estimate: cost incurred to date + estimated cost to complete. If the project team’s cost to complete is optimistic, profit is overstated every month until the truth arrives at once.
Contract assets, contract liabilities and receivables
| Position | Meaning |
|---|---|
| Receivable | An amount billed or certified where the right to payment is unconditional except for time |
| Contract asset | Revenue recognised exceeds the amount billed: work done but not yet billable (often called unbilled revenue) |
| Contract liability | Amounts billed or received exceed revenue recognised, including unearned mobilisation advances |
Retention held by the client is often presented as a contract asset or a separate receivable depending on whether the right to it is still conditional on performance. agree the presentation of retention and mobilisation advances with your auditor.
Worked example: profit, then an overrun
Arena Civil Works signs a fixed-price contract for ₹50 crore. The original estimated total cost is ₹40 crore.
Year 1. Costs incurred ₹12 crore. Progress = 12 ÷ 40 = 30%. Revenue = 30% × ₹50 crore = ₹15 crore. Profit = ₹15 crore − ₹12 crore = ₹3 crore. Certified bills to date are ₹13 crore, so the contract asset is ₹15 crore − ₹13 crore = ₹2 crore.
Year 2. Cumulative costs reach ₹39 crore and the revised estimated total cost is ₹52 crore. The contract will now lose ₹50 crore − ₹52 crore = ₹2 crore overall.
| Item | Working | Amount |
|---|---|---|
| Progress to date | 39 ÷ 52 | 75% |
| Cumulative revenue | 75% × ₹50 crore | ₹37.5 crore |
| Year 2 revenue | ₹37.5 crore − ₹15 crore | ₹22.5 crore |
| Year 2 contract costs | ₹39 crore − ₹12 crore | ₹27 crore |
| Loss on remaining work | (₹50 − ₹37.5) − (₹52 − ₹39) = ₹12.5 − ₹13 crore | ₹0.5 crore |
| Year 2 result | ₹22.5 − ₹27 − ₹0.5 crore | Loss of ₹5 crore |
Check: Year 1 profit ₹3 crore plus Year 2 loss ₹5 crore gives a cumulative loss of ₹2 crore, exactly the expected loss on the whole contract. The ₹0.5 crore is a provision for the loss on the remaining work; under Ind AS it is an onerous contract provision under Ind AS 37, and under AS 7 the expected loss is likewise recognised immediately. Either way, the whole foreseeable loss is in the books in the year it becomes foreseeable, not spread over the remaining work.
Lesson check
Four questions. Get 3 right to complete the lesson. Your progress is saved in this browser.
Lesson 6: Risk, controls, the project MIS and closure
Most contractors that get into trouble do so not on one bad bid but through many small leaks: unbilled variations, unclaimed delays, unrecovered advances and guarantees no one is watching. A monthly project review catches them.
Variations and claims
A variation is a change the client orders: extra items, changed quantities or a different specification. A claim is a request for extra money or time for events the contract puts at the client’s risk, such as late site handover, delayed drawings or suspension of work. Both need paperwork at the time the event happens: written instructions, site records, letters giving notice within the period the contract allows, and a costed statement. Revenue from unapproved variations and claims should be recognised only to the extent it is highly probable that it will not be reversed later. Finance should keep a register of every pending variation and claim, with its value, status and the evidence held.
Liquidated damages
Liquidated damages (LDs) are a pre-agreed amount the client may deduct for late completion, usually a percentage of the contract value per week of delay up to a cap. Under Indian contract law, a court generally allows reasonable compensation up to the stated amount rather than treating the clause as an automatic penalty, but in practice clients deduct LDs from bills and the contractor has to argue for their return. The defences are an extension of time granted for client-caused delay and good records. Provide for LDs when deduction is probable; do not wait for the final bill.
Working capital stress signals
- Unbilled work growing month after month: measurements stuck at site or with the client.
- Certified bills ageing beyond the client’s usual payment cycle.
- Retention and security deposits rising as a share of total receivables.
- Guarantee limits nearly full, blocking new bids.
- Subcontractor and supplier payables being stretched to fund the gap.
The monthly project MIS
| Measure | Why it matters |
|---|---|
| Contract value, approved variations, revised value | What the client will pay if all goes well |
| Cost to date, cost to complete, estimated margin | Early warning of overruns and loss provisions |
| Physical progress versus cost progress | A wide gap suggests a wrong estimate or unbilled work |
| Billed, certified, received, unbilled | Where the cash is stuck |
| Retention held, advance outstanding | Cash due back and recoveries still to come |
| Guarantees by type and expiry | Limit used and dates to act on |
| Pending variations, claims and LD exposure | Upside and downside not yet in the books |
| Days behind schedule | LD risk and extension of time needs |
Closing a project properly
- Final bill submitted with all measurements, variations and price adjustments, and a reconciliation of the client’s deductions.
- Completion certificate obtained; it starts the defect liability period and is a future tender credential.
- Guarantees reduced or returned and the margin released; retention guarantee planned for the defect liability period.
- Tax credits matched: income-tax TDS and GST TDS on every bill reconciled to the credits shown for your PAN and GSTIN.
- Provision for rectification during the defect liability period, based on past experience.
- Subcontractors closed with final accounts and no-claim letters; site stock and plant transferred or sold.
- Lessons recorded: actual versus bid margin, by cost head, fed into the next bid.
Lesson check
Four questions. Get 3 right to complete the lesson. Your progress is saved in this browser.
Final test and certificate
15 questions drawn from a bank, marked on the server. Score 11 or more (70%) for a certificate of completion with a public verification link and an “Add to LinkedIn” button.
Go to the final test- FEMA for importers
- Export compliance
- TDS and GST essentials
- Ind AS foundations
- Close and consolidation
- Internal controls and fraud
- FP&A essentials
- Corporate finance essentials
- Treasury and cash management
- Cost and management accounting
- Import procurement & SCF
- Companies Act compliance
- Payroll compliance
- IFRS, US GAAP and Ind AS
- Excel for finance teams
- AI for finance teams
General information for learning, not professional advice. Laws, rates and standards change: confirm with the official source or your adviser before acting. Last reviewed 15 November 2026.